Green Line Extension Project Field Work (Update for Week of 4/23/10)
Boring Program:
Weeks ending 4/23/10 and 4/30/10:
Within the MBTA right-of-way from Red Bridge in Cambridge to Washington Street in Somerville
On the Archstone property in Cambridge, south of East Street
Boring typically occurs between 7:00 AM and 3:30 PM on weekdays.
Field Survey:
Week ending 4/23/10:
Community Path - Washington Street to the southern tip of Inner Belt Road in Somerville
Utility survey within the MBTA right-of-way starting in Somerville
Week ending 4/30/10:
Bridge survey - Medford Street, Somerville
Bridge survey - Washington Street, Somerville