Magoun Square Paving Set To Commence This Week


On Thursday, October 28th through Friday, October 29th, weather permitting, a City contractor, will be paving Magoun Square during the hours of 6:00 am – 7:00 pm. The following areas will be affected while the work is completed:


Thursday, October 28th, Medford Street will be closed at 6:00 am-7:00 pm between Broadway and Partridge Ave

· Partridge Ave, Trull St, Norwood Ave and Lowell St. will be closed to thru traffic and open to abutters only.

· At 10:00 am the eastbound side of Broadway (CVS side) will be closed and traffic will be shifted to the westbound side and will remain closed until 10:00pm

· CVS parking lot will be closed at Broadway from 10am-10 pm however it will be accessible from Medford street at 7pm


Friday, October 29th, the west bound side of Broadway will be closed at 7:00 am and traffic will be shifted to the eastbound side and will remain closed until 7:00 pm.


Please obey all Detours, No Parking Signs, and Flashing Message Boards. Because these conditions may cause traffic delays, residents are advised to avoid or limit vehicle travel.